City of Toronto — road-occupancy licence & permit bond
Other · Northbridge Construction Group Ltd. · City of Toronto — Procurement
Pending
Request details
- Principal
- Northbridge Construction Group Ltd.
- Description
- City of Toronto — road-occupancy licence & permit bond
Documents
1Timeline & correspondence
- NoteMunicipal road-occupancy permit requires a $25,000 licence & permit bond. Please process offline — permit filing is end of month.Sam Ortega · Jul 13, 2026, 9:30 AM
- ActivityRequest created and submitted to platformNorthbridge · Jul 13, 2026, 9:00 AM
- ActivityUnderwriter review noteMarcus Webb (AE) · Jul 13, 2026, 12:00 AM
Miscellaneous bond — processing
Licence & Permit. Processed offline, then upload the finished bond here — it attaches to the record and the timeline.
Licence & permit template — test data pending from Steph (stubbed).
Marks the request Issued and attaches the PDF to the record.
Clients can't edit a Pending request directly — changes route through platform for review/approval.
Pending reason
Internal only — not shown to the client.
Facility fit · Northbridge
Working authorityIn place
Utilization99% · $202.1M / $205.0M
Doesn't consume the facility until a bond is requested.
View facility utilization