SuretyX
Bowmont Development 40 — Bonds

Ville de Montréal — Transit Maintenance Facility

Performance Bond · Trillium Development 41 · Région de Montréal — Travaux publics

Issued#INT-8169

Request details

all submitted fields
Principal
Trillium Development 41
Project title
Ville de Montréal — Transit Maintenance Facility
Obligee
Région de Montréal — Travaux publics
Obligee address
275 Rue Notre-Dame E, Montréal, QC
Obligee email
appels.offres@montreal.ca
Contract value
$7.5M
Contract date
—
Date required
2026-04-18
Start date
2025-02-22
Completion Date
2028-11-24
Validity period
—
Delivery
Electronic
Liquidated damages
—
Warranty
12 months

Documents

2

Timeline & correspondence

  1. Activity
    Request created and submitted to platform
    Trillium Development 41 · Apr 14, 2026, 8:00 AM
  2. Activity
    Bond issued (INT-8169)
    platform · Apr 14, 2026, 8:00 AM
  3. Activity
    Underwriter review note
    Sophie Bélanger (AE) · Apr 14, 2026, 12:00 AM
  4. Activity
    Surety quote — Trisura
    POA-TRS-1204 (N. Fournier) · Apr 14, 2026, 12:00 AM

Status & actions

Facility fit · Trillium Development 41

Working authorityNone
Utilization56% · $113.7M / $204.0M

Adds $7.5M to backlog on issue.

View facility utilization

Premium

$50,600
combined premium

One combined premium for the pair — Performance + L&M Payment bonds.

Premium is never printed on the bond.

Signing & delivery

E-signature executed via Xenex (out of scope for V1) and uploaded back to the record.