Part of the Cedar group facility — group is at 66% ($276.5M / $419.0M). This entity contributes $98.8M on its own $139.0M limit.View group
Bids & consents YTD
3
2 bid · 1 consent
Successful tenders
2
marked Low Bid
% successful
50%
Low Bid of 4 decided
Open exposure
$98.8M
71% of $139.0M

Facility utilization — bid vs. final exposure

This entity's own facility · live
71%of $139.0M own facility
$98.8M drawn
Final-bond exposure
$43.6M
cost-to-complete + bonded since 2026-02-15
Bid exposure
$55.2M
open tenders as of today · est. price
Available
$40.2M
remaining capacity

Latest WOH as of 2026-02-15 · final bonds since 2026-02-15 · outstanding bids as of today · current utilization as of today.

Working authoritySingle job $52.0MAggregate $139.0Msurety since 2014

Derived live from the bond store — marking a bid Unsuccessful or Expired removes it from bid exposure in real time.

Exposure report

Total surety exposure — sum of issued bond penalties$5.8M
Bid bonds5 bonds
ProjectBid dateValidityPenalty (exposure)
Transit Agency — Pedestrian Overpass
Minister of National Revenue (Canada Revenue Agency) · 10% bid bond on $15.5M tender
2026-03-28—$1.6M
Health Authority — Data Centre Fit-up
Metrolinx · 10% bid bond on $4.9M tender
2026-06-26—$490K
Transit Agency — Tunnel Ventilation
Minister of National Revenue (Canada Revenue Agency) · 10% bid bond on $15.5M tender
2025-06-19—$1.6M
Health Authority — Pumping Station Upgrade
Minister of National Revenue (Canada Revenue Agency) · 10% bid bond on $6.2M tender
2025-12-16—$620K
University — Library Renovation
BC Ministry of Transportation · 10% bid bond on $15.9M tender
2025-02-24—$1.6M
Bid bonds subtotal$5.8M
Final bonds — Performance & Payment0 bonds
ProjectCompletion datePenalty (exposure)
No issued final bonds.

Penalty at risk: bid bonds at their bid % of the tender (e.g. 10% of a $5M job = $500K); final bonds at the full contract (Performance 50% + L&M 50% = 100%). Issued bonds only — lost, expired, draft, and pending bonds are excluded.

Pipeline & miscellaneous

Pre-qual / opportunities · Other / Misc
Other / Miscellaneous

No miscellaneous bonds.

Account team

Surety company
Trisura Guarantee Insurance Company
Underwriter
N. Fournier
platform Account Executive
Aaron Sandhu
platform Account Manager
Mei Lin

Agreements vault

Versioned · newest on top