Birchwood Development 43

Heavy Civil · Montréal, QC · Montréal office · AM Élise Caron

Client profile 86% completeoptional — won't block requests

Notes & reminders

Add a note

No notes yet.

Dated, categorized log with attached files/emails. AI search + executive summaries arrive later.

Reminders (on record)

No reminders.

Visible to anyone viewing the account; also on the assignee's dashboard.

Part of the Bowmont Development 40 group facility — group is at 56% ($113.7M / $204.0M). This entity contributes $27.2M on its own $30.0M limit.View group
Bids & consents YTD
3
2 bid · 1 consent
Successful tenders
0
marked Low Bid
% successful
0%
Low Bid of 1 decided
Open exposure
$27.2M
91% of $30.0M

Facility utilization — bid vs. final exposure

This entity's own facility · live
91%of $30.0M own facility
$27.2M drawn
Final-bond exposure
$11.3M
cost-to-complete + bonded since 2026-02-21
Bid exposure
$15.9M
open tenders as of today · est. price
Available
$2.8M
remaining capacity

Latest WOH as of 2026-02-21 · final bonds since 2026-02-21 · outstanding bids as of today · current utilization as of today.

Working authoritySingle job $10.0MAggregate $30.0Msurety since 2019

Derived live from the bond store — marking a bid Unsuccessful or Expired removes it from bid exposure in real time.

Exposure report

Total surety exposure — sum of issued bond penalties$11.1M
Bid bonds1 bond
ProjectBid dateValidityPenalty (exposure)
Ville de Montréal — Wastewater Treatment Upgrade
City of Toronto — Procurement · 10% bid bond on $1.9M tender
2026-03-01—$190K
Bid bonds subtotal$190K
Final bonds — Performance & Payment4 bonds
ProjectCompletion datePenalty (exposure)
Ville de Montréal — Data Centre Fit-up
BC Ministry of Transportation · INT-E-7774 · Performance 50% + L&M 50% on $3.7M contract
2027-06-24$3.7M
Ville de Montréal — LRT Station Finishes
Infrastructure Ontario · TRV-5066 · Performance 50% + L&M 50% on $3.8M contract
2027-08-19$3.8M
Ville de Montréal — Water Main Renewal
Region of Peel · INT-4866 · Performance 50% + L&M 50% on $800K contract
2028-05-10$800K
Ville de Montréal — Recreation Centre
Region of Peel · INT-E-3650 · Performance 50% + L&M 50% on $2.6M contract
2027-05-21$2.6M
Final bonds — Performance & Payment subtotal$10.9M

Penalty at risk: bid bonds at their bid % of the tender (e.g. 10% of a $5M job = $500K); final bonds at the full contract (Performance 50% + L&M 50% = 100%). Issued bonds only — lost, expired, draft, and pending bonds are excluded.

Pipeline & miscellaneous

Pre-qual / opportunities · Other / Misc
Other / Miscellaneous

No miscellaneous bonds.

Account team

Surety company
Intact Insurance Company
Underwriter
D. Armstrong
platform Account Executive
Sophie Bélanger
platform Account Manager
Élise Caron

Agreements vault